Korean disclosure
HDC Holdings's subsidiary was selected as the construction contractor for the 13 district redevelopment project in Yeonsan.
Unofficial English translation by ChickenStock; the Korean original prevails. Korean page · Original filing on DART ↗
Highlights
Translated AI summaryHDC Holdings's subsidiary was selected as the construction contractor for the 13 district redevelopment project in Yeonsan. The estimated construction cost is KRW 281.2 billion, representing 6.8% of recent sales of KRW 4.147 trillion. The estimated construction cost will be finalized upon execution of the construction contract and may change during project execution.
The subsidiary was selected as the construction contractor for the 13 district redevelopment project in Yeonsan on October 3, 2026.
The estimated construction cost is KRW 281.2 billion (excluding value-added tax) and represents 6.8% of recent sales of KRW 4.147 trillion.
The estimated construction cost will be finalized upon execution of the construction contract.
The amount may change during project execution, and finalized details will be disclosed upon execution of the main contract.
An AI model translated the Korean summary of this filing into English; every number is carried over from the Korean original. Reference information, not investment advice.
Key figures
- Estimated construction cost
- KRW 281.2 billion
- Recent sales
- KRW 4.147 trillion
- Ratio to sales
- 6.8%
- Selection date
- October 3, 2026
- Project scale
- 3 basement floors to 34 above-ground floors, 5 buildings, 720 units
Filing facts
- Filing type
- Material Management Information
- Report name
- Material Management Information for Investment Decisions (Subsidiary)
- Filed
- Oct 6, 2026
- Receipt number
- 20261006800172