The company said on November 21, 2025 that its subsidiary Public Service Company of Colorado (PSCo) filed an electric rate increase request with the Colorado Public Utilities Commission. The request seeks revenue of $356 million, or 9.9%, and totals $526 million including rider roll-ins.

8-KOther EventsFiled Period of report Summary published (UTC)

Key points

AI summary
  1. The company said on November 21, 2025 that its subsidiary Public Service Company of Colorado (PSCo) filed an electric rate increase request with the Colorado Public Utilities Commission. The request seeks revenue of $356 million, or 9.9%, and totals $526 million including rider roll-ins.

  2. Xcel Energy said the request is based on a 9.8% return on equity, a 55% equity ratio, a 2025 test year and a projected rate base of $13 billion.

  3. The company disclosed that the base rate increase request, net of rider roll-ins, of $356 million consists of distribution system investment of $294 million, liability insurance of $65 million, operating costs of $51 million, changes in cost of capital of $49 million, other items of $17 million and coal retirements of $(120) million.

  4. PSCo said the request includes rider recovery of costs tied to extending operations at Comanche Unit 2. The company also said a CPUC decision and implementation of final rates are expected in Q3 2026.

Summary

AI-written

Analysis scope · Filing bodyWe analyzed the filing body and confirmed exhibits. This is not a review of other exhibits, investor presentations or the full earnings call.

Colorado Electric Rate Increase Request

The company said on November 21, 2025 that its subsidiary Public Service Company of Colorado (PSCo) filed an electric rate increase request with the Colorado Public Utilities Commission. The request seeks revenue of $356 million, or 9.9%, and totals $526 million including rider roll-ins.

Source · Based on the filing body and exhibits

Basis for the Rate Request

Xcel Energy said the request is based on a 9.8% return on equity, a 55% equity ratio, a 2025 test year and a projected rate base of $13 billion.

Source · Based on the filing body and exhibits

Components of the Base Rate Increase Request

The company disclosed that the base rate increase request, net of rider roll-ins, of $356 million consists of distribution system investment of $294 million, liability insurance of $65 million, operating costs of $51 million, changes in cost of capital of $49 million, other items of $17 million and coal retirements of $(120) million.

Source · Based on the filing body and exhibits

Comanche Unit 2 and Decision Timing

PSCo said the request includes rider recovery of costs tied to extending operations at Comanche Unit 2. The company also said a CPUC decision and implementation of final rates are expected in Q3 2026.

Source · Based on the filing body and exhibits

AI summarized the filing and translated the summary into English; it may differ from the original. For reference only, not investment advice. AI translated the published Korean report into English. Figures are copied as filed, not recalculated.

Original filing

The filing as submitted to SEC EDGAR. You can check the figures and statements of this summary against it.

Source: SEC EDGAR (U.S. Securities and Exchange Commission). Item captions are the SEC's. The summary is for reference only and is not investment advice.