Duke Energy said Duke Energy Progress and the Office of Regulatory Staff reached a partial settlement in connection with the base rate proceeding before the Public Service Commission of South Carolina on October 27, 2025. The settlement is subject to review and approval by the PSCSC.

8-KRegulation FD DisclosureFiled Period of report Summary published (UTC)

Key points

AI summary
  1. Duke Energy said Duke Energy Progress and the Office of Regulatory Staff reached a partial settlement in connection with the base rate proceeding before the Public Service Commission of South Carolina on October 27, 2025. The settlement is subject to review and approval by the PSCSC.

  2. The company said the annual customer rate increase under the settlement is approximately $40 million (representing an average increase of 6.5% across retail customers), net of $10 million in annual PTC flow-back. The original filing requested an overall increase in annual retail revenues of approximately $75 million.

  3. Duke Energy said the settlement includes a return on equity of 9.99%, a capital structure of 53% equity and 47% debt, an overall rate of return of 7.2%, and a South Carolina retail rate base of $2.2 billion. The original filing requested 10.85%, 7.65% and $2.3 billion.

  4. The company said the settlement supports flowing back $10 million in PTC annually to customers over a 24-month period and increasing the annual storm reserve funding from $3 million to $6 million. It also requested that new rates go into effect no later than February 1, 2026.

Summary

AI-written

Analysis scope · Filing body and confirmed press-release exhibitWe analyzed the filing body and confirmed exhibits. This is not a review of other exhibits, investor presentations or the full earnings call.

Partial Settlement Reached and Subject to Approval

Duke Energy said Duke Energy Progress and the Office of Regulatory Staff reached a partial settlement in connection with the base rate proceeding before the Public Service Commission of South Carolina on October 27, 2025. The settlement is subject to review and approval by the PSCSC.

Source · Based on the filing body and exhibits

Rate Increase and Adjustments from Original Filing

The company said the annual customer rate increase under the settlement is approximately $40 million (representing an average increase of 6.5% across retail customers), net of $10 million in annual PTC flow-back. The original filing requested an overall increase in annual retail revenues of approximately $75 million.

Source · Based on the filing body and exhibits

Return on Equity and Capital Structure in Settlement

Duke Energy said the settlement includes a return on equity of 9.99%, a capital structure of 53% equity and 47% debt, an overall rate of return of 7.2%, and a South Carolina retail rate base of $2.2 billion. The original filing requested 10.85%, 7.65% and $2.3 billion.

Source · Based on the filing body and exhibits

PTC Flow-Back, Storm Reserve Funding and New Rate Effective Date

The company said the settlement supports flowing back $10 million in PTC annually to customers over a 24-month period and increasing the annual storm reserve funding from $3 million to $6 million. It also requested that new rates go into effect no later than February 1, 2026.

Source · Based on the filing body and exhibits

AI summarized the filing and translated the summary into English; it may differ from the original. For reference only, not investment advice. AI translated the published Korean report into English. Figures are copied as filed, not recalculated.

Original filing

The filing as submitted to SEC EDGAR. You can check the figures and statements of this summary against it.

Source: SEC EDGAR (U.S. Securities and Exchange Commission). Item captions are the SEC's. The summary is for reference only and is not investment advice.