Dominion Energy logoDominion Energy D

The company said estimated total project costs for CVOW, including contingency and excluding financing costs, rose from about $11.2 billion to about $11.5 billion, and that completion is now expected in early 2027.

8-KRegulation FD DisclosureFiled Period of report Summary published (UTC)

Key points

AI summary
  1. The company said estimated total project costs for CVOW, including contingency and excluding financing costs, rose from about $11.2 billion to about $11.5 billion, and that completion is now expected in early 2027.

  2. The company said the current capital budget of $11.5B reflects actual and estimated tariffs of $580M and $228M associated with the BOEM Suspension Order. It cited construction delays related to the BOEM Suspension Order ($228M) and incremental tariff recognition ($137M) as drivers of the cost increase.

  3. The company said it received an order from BOEM on December 22, 2025 to suspend CVOW-related activities for 90 days for national security reasons, and that a federal court blocked enforcement of the order with a preliminary injunction on January 16, 2026, allowing offshore work to resume.

  4. The company said that as of December 31, 2025, project-to-date investment was about $9.3B and remaining project costs were about $2.2B. It said unused contingency was $155M, compared with $206M last quarter.

Summary

AI-written

Analysis scope · Filing body and confirmed press-release exhibitWe analyzed the filing body and confirmed exhibits. This is not a review of other exhibits, investor presentations or the full earnings call.

CVOW Total Project Cost Estimate Revised

The company said estimated total project costs for CVOW, including contingency and excluding financing costs, rose from about $11.2 billion to about $11.5 billion, and that completion is now expected in early 2027.

Source · Based on the filing body and exhibits

Cost Increase Drivers: BOEM Suspension Order and Tariffs

The company said the current capital budget of $11.5B reflects actual and estimated tariffs of $580M and $228M associated with the BOEM Suspension Order. It cited construction delays related to the BOEM Suspension Order ($228M) and incremental tariff recognition ($137M) as drivers of the cost increase.

Source · Based on the filing body and exhibits

BOEM Suspension Order and Preliminary Injunction

The company said it received an order from BOEM on December 22, 2025 to suspend CVOW-related activities for 90 days for national security reasons, and that a federal court blocked enforcement of the order with a preliminary injunction on January 16, 2026, allowing offshore work to resume.

Source · Based on the filing body and exhibits

Remaining Costs and Contingency Status

The company said that as of December 31, 2025, project-to-date investment was about $9.3B and remaining project costs were about $2.2B. It said unused contingency was $155M, compared with $206M last quarter.

Source · Based on the filing body and exhibits

AI summarized the filing and translated the summary into English; it may differ from the original. For reference only, not investment advice. AI translated the published Korean report into English. Figures are copied as filed, not recalculated.

Original filing

The filing as submitted to SEC EDGAR. You can check the figures and statements of this summary against it.

Source: SEC EDGAR (U.S. Securities and Exchange Commission). Item captions are the SEC's. The summary is for reference only and is not investment advice.