The company said the U.S. District Court for the Eastern District of Virginia granted Virginia Power's request for a preliminary injunction against the BOEM Order, which directed a suspension of all CVOW-related activities for 90 days, issued on January 16, 2026.
Key points
AI summaryThe company said the U.S. District Court for the Eastern District of Virginia granted Virginia Power's request for a preliminary injunction against the BOEM Order, which directed a suspension of all CVOW-related activities for 90 days, issued on January 16, 2026.
The company disclosed that the Bureau of Ocean Energy Management of the U.S. Department of the Interior suspended work on the Coastal Virginia Offshore Wind (CVOW) project for 90 days through a Director's Order dated December 22, 2025. The order directed OSW Project LLC to halt all ongoing CVOW-related activities.
The company said Virginia Power will resume work on CVOW while its lawsuit challenging the agency's action proceeds in the courts. In the press release, the company said it is focused on restarting work safely and, separate from its legal challenge, will continue to seek a durable resolution through cooperation with the federal government.
The company said its subsidiary Virginia Power holds 50% of the membership interests in OSW Project LLC. According to the press release, CVOW will consist of 176 offshore wind energy turbines with a total generating capacity of 2.6 gigawatts, enough to power up to 660,000 homes.
Summary
AI-writtenAnalysis scope · Filing body and confirmed press-release exhibitWe analyzed the filing body and confirmed exhibits. This is not a review of other exhibits, investor presentations or the full earnings call.
Court Grants Injunction Against 90-Day CVOW Suspension Order
The company said the U.S. District Court for the Eastern District of Virginia granted Virginia Power's request for a preliminary injunction against the BOEM Order, which directed a suspension of all CVOW-related activities for 90 days, issued on January 16, 2026.
Source · Based on the filing body and exhibits
BOEM Order Issue Date and Scope of Suspension
The company disclosed that the Bureau of Ocean Energy Management of the U.S. Department of the Interior suspended work on the Coastal Virginia Offshore Wind (CVOW) project for 90 days through a Director's Order dated December 22, 2025. The order directed OSW Project LLC to halt all ongoing CVOW-related activities.
Source · Based on the filing body and exhibits
CVOW Work to Resume During Lawsuit
The company said Virginia Power will resume work on CVOW while its lawsuit challenging the agency's action proceeds in the courts. In the press release, the company said it is focused on restarting work safely and, separate from its legal challenge, will continue to seek a durable resolution through cooperation with the federal government.
Source · Based on the filing body and exhibits
OSW Project LLC Stake and CVOW Turbine Capacity
The company said its subsidiary Virginia Power holds 50% of the membership interests in OSW Project LLC. According to the press release, CVOW will consist of 176 offshore wind energy turbines with a total generating capacity of 2.6 gigawatts, enough to power up to 660,000 homes.
Source · Based on the filing body and exhibits
AI summarized the filing and translated the summary into English; it may differ from the original. For reference only, not investment advice. AI translated the published Korean report into English. Figures are copied as filed, not recalculated.