Dominion Energy said on December 22, 2025 that BOEM issued a Director's Order, effective immediately, to OSW Project LLC to suspend all ongoing activities related to the Coastal Virginia Offshore Wind (CVOW) project for 90 days.
Key points
AI summaryDominion Energy said on December 22, 2025 that BOEM issued a Director's Order, effective immediately, to OSW Project LLC to suspend all ongoing activities related to the Coastal Virginia Offshore Wind (CVOW) project for 90 days.
The company said its subsidiary Virginia Electric and Power Company holds 50% of the membership interests of OSW Project LLC, the entity subject to the suspension order.
Dominion Energy argued in a press release that CVOW is essential for American national security and meeting Virginia's rapidly growing energy needs, and that suspending it for any length of time will threaten grid reliability for some critical facilities and affect thousands of jobs.
The company said CVOW is located 27 to 44 miles offshore, its 2 pilot turbines have been operating for 5 years, and the project is expected to generate 2,600 megawatts within months. It added that the project underwent a cost-benefit review by Virginia state regulators in 2022.
Summary
AI-writtenAnalysis scope · Filing body and confirmed press-release exhibitWe analyzed the filing body and confirmed exhibits. This is not a review of other exhibits, investor presentations or the full earnings call.
BOEM Issues 90-Day Work Suspension Order for CVOW Project
Dominion Energy said on December 22, 2025 that BOEM issued a Director's Order, effective immediately, to OSW Project LLC to suspend all ongoing activities related to the Coastal Virginia Offshore Wind (CVOW) project for 90 days.
Source · Based on the filing body and exhibits
Subsidiary Holds 50% Membership Interest in OSW Project LLC
The company said its subsidiary Virginia Electric and Power Company holds 50% of the membership interests of OSW Project LLC, the entity subject to the suspension order.
Source · Based on the filing body and exhibits
Company States Position on Power Demand and Grid Reliability
Dominion Energy argued in a press release that CVOW is essential for American national security and meeting Virginia's rapidly growing energy needs, and that suspending it for any length of time will threaten grid reliability for some critical facilities and affect thousands of jobs.
Source · Based on the filing body and exhibits
Company Outlines CVOW Progress and Scale
The company said CVOW is located 27 to 44 miles offshore, its 2 pilot turbines have been operating for 5 years, and the project is expected to generate 2,600 megawatts within months. It added that the project underwent a cost-benefit review by Virginia state regulators in 2022.
Source · Based on the filing body and exhibits
AI summarized the filing and translated the summary into English; it may differ from the original. For reference only, not investment advice. AI translated the published Korean report into English. Figures are copied as filed, not recalculated.
Original filing
The filing as submitted to SEC EDGAR. You can check the figures and statements of this summary against it.
Loading the filing text…